Mission Timeline
Photometric Observations of Exoplanet Transits (POET)
Past
May 2018 - September 2019
Science Maturation Study
Current
Current -
August 2022
Space Technology Development Program (STDP) to develop the Optical Telescope Assembly (OTA)
Future
September 2022 - August 2023
1 year Mission and System Definition
(Phase 0 and A)
Sept 2023 - August 2026:
3 year Design, Manufacturing, Launch and Commissioning
(Phase BCD)
Launch to occur mid-2026
Sept 2026 - August 2028
2 year Nominal Operations (Phase E)
After the nominal operations end a mission extension will be investigated
The mission ends with 2 months of Decommissioning
(Phase F)